Masonry Work Productivity Rate

You are currently viewing Masonry Work Productivity Rate
Masonry Work Productivity Rate

The data written below for masonry work productivity rate are the average output per hour of the task or activity. The described activity has a recommended list of teams for labor and equipment. Please take note that these are suggested values and for reference only. Each project has a different approach. Factors, wastage and allowances should be considered while doing estimates.

The list of activities indicated below are for placement of concrete blocks, installation of reinforcement, grouting and mortar.

For other civil works productivity rates, please check below the list of items:
– Rebar installation man-hours, please see the link: REBAR PRODUCTIVITY RATE
– Concreting works and installation man-hours, please see the link: CONCRETE WORK PRODUCTIVITY RATE

For other material price list, please check below the list of items:
– Reinforced concrete pipe, please see the link: RCP PIPE PRICE LIST
– Ready mixed concrete, please see the link: RMC PRICE LIST
– Rebar steel price list, please see the link: REBAR PRICE LIST
– I beam price list, please see the link: I-BEAM PRICE LIST

MASONRY PRODUCTIVITY WORK

CONCRETE BLOCKS

TEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Concrete Hollow Blocks, tooled joints (2-sides) 100mm thick Square Meters 0.250
4.000
2.000
0.375

0.250

0.500

0.125
0.125
0.125
0.500
Foreman
Mason
Laborer
Equip. Opt.
Batch Mixer
Power Tools
Crane
Fork Lift
Truck
Lifting Equipment
1.17 0.29 Hr / Square Meters
2 Concrete Hollow Blocks, tooled joints (2-sides) 150mm thick Square Meters 1.32 0.33 Hr / Square Meters
3 Concrete Hollow Blocks, tooled joints (2-sides) 200mm thick Square Meters 1.56 0.39 Hr / Square Meters
4 Concrete Hollow Blocks, tooled joints (2-sides) 250mm thick Square Meters 1.75 0.44 Hr / Square Meters
5 Concrete Hollow Blocks, tooled joints (2-sides) 300mm thick Square Meters 2.04 0.51 Hr / Square Meters
6 Concrete Hollow Blocks, No tooled joints (2-sides) 100mm thick Square Meters 1.06 0.26 Hr / Square Meters
7 Concrete Hollow Blocks, No tooled joints (2-sides) 150mm thick Square Meters 1.19 0.30 Hr / Square Meters
8 Concrete Hollow Blocks, No tooled joints (2-sides) 200mm thick Square Meters 1.41 0.35 Hr / Square Meters
9 Concrete Hollow Blocks, No tooled joints (2-sides) 250mm thick Square Meters 1.58 0.40 Hr / Square Meters

REINFORCEMENT

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Anchor bolts w/ nuts and washer 12mmDiameter, 200mm Length Piece 1.00 Mason 0.07 0.00 Hr / Piece
2 Anchor bolts w/ nuts and washer 12mmDiameter, 300mm Length Piece 0.08 0.00 Hr / Piece
3 Anchor bolts w/ nuts and washer 16mmDiameter, 300mm Length Piece 0.09 0.00 Hr / Piece
4 Anchor bolts w/ nuts and washer 20mmDiameter, 300mm Length Piece 0.10 0.00 Hr / Piece
5 Control Joint (PVC or Rubber) 100mm thick wall Linear Meters 0.05 0.00 Hr / Linear Meters
6 Control Joint (PVC or Rubber) 150mm thick wall Linear Meters 0.06 0.00 Hr / Linear Meters
7 Control Joint (PVC or Rubber) 200mm thick wall Linear Meters 0.07 0.00 Hr / Linear Meters
8 Control Joint (PVC or Rubber) 300mm thick wall Linear Meters 0.10 0.00 Hr / Linear Meters
9 Rebar Joint, horizontal placement ≤ 12mm bars Kilograms 1.00 2.00 Mason Laborer 0.05 0.00 Hr / Kilograms
10 Rebar Joint, horizontal placement 16mm & 20mm bars Kilograms 0.03 0.00 Hr / Kilograms
11 Rebar Joint, vertical placement ≤ 12mm bars Kilograms 0.07 0.00 Hr / Kilograms
12 Rebar Joint, vertical placement 16mm & 20mm bars Kilograms 0.04 0.00 Hr / Kilograms
13 Reinforcing Wire Strip ≤ 150mm Wide Linear Meters 0.01 0.00 Hr / Linear Meters
14 Reinforcing Wire Strip ≥150mm & ≤300mm Wide Linear Meters 0.02 0.00 Hr / Linear Meters
15 Cavity Truss ≤ 150mm Wide Linear Meters 0.01 0.00 Hr / Linear Meters
16 Cavity Truss ≥150mm & ≤300mm Wide Linear Meters 0.02 0.00 Hr / Linear Meters

GROUTING AND MORTAR

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Mortar w/ masonry cement, field mix 1:1:6 Mix (type M) Cubic Meters 0.125
1.000
2.000
1.000
Foreman
Mason
Laborer
Batch Mixer
4.69 1.50 Hr / Cubic Meters
2 Mortar w/ masonry cement, field mix 1:3 Mix (type N) Cubic Meters 4.69 1.50 Hr / Cubic Meters
3 Mortar w/ portland cement and lime, field mix 1:1/4:3 Mix (type M) Cubic Meters 4.69 1.50 Hr / Cubic Meters
4 Mortar w/ portland cement and lime, field mix 1:1:16 Mix (type N) Cubic Meters 4.69 1.50 Hr / Cubic Meters
5 Grouting CHB by Hand 100mm thick Square Meters 1.000
1.000
Mason
Laborer
0.80 0.00 Hr / Square Meters
6 Grouting CHB by pump 150mm thick Square Meters 1.00
2.00
1.00


1.00
Mason
Laborer
Light Eqpt. Opt.
Grouting Pump Set
0.26 0.19 Hr / Square Meters
7 Grouting CHB by pump 200mm thick Square Meters 0.35 0.26 Hr / Square Meters
8 Grouting CHB by pump 300mm thick Square Meters 0.60 0.45 Hr / Square Meters
9 Grouting cavity walls 50mm Space Square Meters 0.18 0.13 Hr / Square Meters
10 Grouting cavity walls 75mm Space Square Meters 0.26 0.20 Hr / Square Meters
11 Grouting cavity walls 100mm Space Square Meters 0.35 0.26 Hr / Square Meters
12 Grouting cavity walls 150mm Space Square Meters 0.52 0.39 Hr / Square Meters
13 Grouting door frames 900mm x 2100mm Opening 0.49 0.37 Hr / Opening
14 Grouting door frames 1800mm x 2100mm Opening 0.70 0.53 Hr / Opening

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Don’t forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our Facebook page for social media updates.

facebook.com/theprojectestimate