The data written below for concrete work productivity rate are the average output per hour of the task or activity. The described activity has a recommended list of teams for labor and equipment. Please take note that these are suggested values and for reference only. Each project has a different approach. Factors, wastage and allowances should be considered while doing estimates.
The list activities indicated below are for Cast-In-Place concrete work. Please take note of the remarks in the activity if the output accounts the productivity for formworks, steelworks and works for finishes.
For other civil works productivity rates, please check below the list of items:
– Masonry works and installation man-hours, please see the link: MASONRY WORK PRODUCTIVITY RATE
– Rebar installation man-hours, please see the link: REBAR PRODUCTIVITY RATE
For other material price list, please check below the list of items:
– Reinforced concrete pipe, please see the link: RCP PIPE PRICE LIST
– Ready mixed concrete, please see the link: RMC PRICE LIST
– Rebar steel price list, please see the link: REBAR PRICE LIST
– I beam price list, please see the link: I-BEAM PRICE LIST
CONCRETE WORK PRODUCTIVITY RATE
BASE
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Base, granolithic | 25 mm x 127mm | Incld. forms & rebar | Linear Meters | 0.125 2.000 1.000 1.000 1.000 2.000 | Foreman Mason Carpenter Steelman Laborer Finishing Eqpt | 0.57 | 0.22 | Hr / Linear Meters |
2 | Base, granolithic | 25 mm x 127mm (High cove) | Incld. forms & rebar | Linear Meters | 0.77 | 0.30 | Hr / Linear Meters |
BEAMS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Beams, 745 kg/m | 3.0 m span | Incld. forms & rebar | Cubic Meters | 1.000 10.00 4.000 0.250 1.000 0.375 0.125 0.500 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
27.30 | 8.61 | Hr / Cubic Meters |
2 | Beams, 745 kg/m | 7.5 m span | Incld. forms & rebar | Cubic Meters | 22.02 | 6.94 | Hr / Cubic Meters |
COLUMNS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Square Columns, @ 4.2 m high | 300mm x 300mm (max) | Incld. forms & rebar | Cubic Meters | 1.000 10.00 4.000 0.250 1.000 0.375 0.125 0.500 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equipt. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
50.56 | 15.94 | Hr / Cubic Meters |
2 | Square Columns, @ 4.2 m high | 600mm x 600mm (max) | Incld. forms & rebar | Cubic Meters | 29.67 | 9.36 | Hr / Cubic Meters | ||
3 | Square Columns, @ 4.2 m high | 900mm x 900mm (max) | Incld. forms & rebar | Cubic Meters | 23.14 | 7.30 | Hr / Cubic Meters | ||
4 | Rectangular Columns, @ 4.2 m high | 300mm x 1600mm (max) | Incld. forms & rebar | Cubic Meters | 30.33 | 9.57 | Hr / Cubic Meters | ||
5 | Round Columns, Tied, @ 4.2 m high | 300mm Diameter | Incld. forms & rebar | Cubic Meters | 1.000 9.000 5.000 0.250 1.00 0.375 0.125 0.500 0.125 2.000 |
Foreman Carpenter &Steelman Laborer Mason Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
34.13 | 6.56 | Hr / Cubic Meters |
6 | Round Columns, Tied, @ 4.2 m high | 600mm Diameter | Incld. forms & rebar | Cubic Meters | 22.75 | 4.38 | Hr / Cubic Meters | ||
7 | Round Columns, Tied, @ 4.2 m high | 900mm Diameter | Incld. forms & rebar | Cubic Meters | 16.65 | 3.20 | Hr / Cubic Meters | ||
8 | Max Rebar, Round Columns, Tied, @ 4.2 m high | 900mm Diameter | Incld. forms & rebar | Cubic Meters | 28.44 | 5.47 | Hr / Cubic Meters |
ELEVATED SLABS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Elevated Flat Slabs, Suspended, @ 600kg/m2 | 6.0m Span | Incld. forms, rebar, & finish | Cubic Meters | 1.000 10.00 4.000 0.250 1.000 0.375 0.125 0.500 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equipt. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
9.29 | 2.93 | Hr / Cubic Meters |
2 | Elevated Flat Slabs, Suspended, @ 600kg/m2 | 8.4m Span | Incld. forms, rebar, & finish | Cubic Meters | 6.83 | 2.15 | Hr / Cubic Meters | ||
3 | Elevated Flat Slabs, Suspended, @ 600kg/m2 | 4.6m Span | Incld. forms, rebar, & finish | Cubic Meters | 9.10 | 2.87 | Hr / Cubic Meters | ||
4 | Elevated Flat Slabs, Suspended, @ 600kg/m2 | 7.4m Span | Incld. forms, rebar, & finish | Cubic Meters | 7.58 | 2.39 | Hr / Cubic Meters | ||
5 | Elevated Waffle Slabs, Suspended, @ 600 kg/m2 | 6.0m Span | Incld. forms, rebar, & finish | Cubic Meters | 1.000 10.00 4.000 0.250 1.000 0.375 0.125 0.500 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
11.38 | 3.59 | Hr / Cubic Meters |
6 | Elevated Waffle Slabs, Suspended, @ 600 kg/m2 | 9.2m Span | Incld. forms, rebar, & finish | Cubic Meters | 9.10 | 2.87 | Hr / Cubic Meters | ||
7 | Elevated Joist Slab, Suspended, @ 600 kg/m2 | 4.6m Span , 762 Pans | Incld. forms, rebar, & finish | Cubic Meters | 11.57 | 3.65 | Hr / Cubic Meters | ||
8 | Elevated Joist Slab, Suspended, @ 600 kg/m2 | 7.2m Span, 762 Pans | Incld. forms, rebar, & finish | Cubic Meters | 9.48 | 2.99 | Hr / Cubic Meters | ||
9 | Elevated one way beam, Suspended, @ 600 kg/m2 | 7.6m Span | Incld. forms, rebar, & finish | Cubic Meters | 14.37 | 4.53 | Hr / Cubic Meters | ||
10 | Elevated two way beam, Suspended, @ 600 kg/m2 | 7.6m Span | Incld. forms, rebar, & finish | Cubic Meters | 12.47 | 3.93 | Hr / Cubic Meters | ||
11 | Elevated slabs (concreting & finish only) | 150mm Thick | Incld. forms, rebar, & finish | Square Meters | 0.5 6.00 2.00 2.00 1.00 1.00 2.00 2.00 |
Foreman Laborer Mason Carpenter Equip. Opt. Concrete Pump Concrete Vibrator Finishing Eqpt |
0.22 | 0.10 | Hr / Square Meters |
12 | Elevated slabs (concreting & finish only) | 64 mm Thick Floor | Incld. forms, rebar, & finish | Square Meters | 0.22 | 0.10 | Hr / Square Meters |
FOUNDATION
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Spread Footings | ≤ 0.75m3 | Incld. forms, rebar, & finish | Cubic Meters | 1.000 5.000 4.000 0.250 0.250 0.375 0.125 0.250 0.125 2.000 |
Foreman Carpenter &Steelman Laborer Mason Equip. Opt. Concrete Vibrator Concrete Pump Crane Truck Power Tools |
5.88 | 1.61 | Hr / Cubic Meters |
2 | Spread Footings | ≥ 4.0m3 | Incld. forms & rebar | Cubic Meters | 4.90 | 1.34 | Hr / Cubic Meters | ||
3 | Mat Foundation | ≥ 1000m3 | Incld. forms & rebar | Cubic Meters | 0.500 7.000 0.250 4.000 0.500 0.250 0.250 0.250 0.125 2.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Crane Truck Concrete Pump Power Tools |
4.20 | 0.99 | Hr / Cubic Meters |
4 | Mat Foundation | ≥ 25 m3 to ≤ 500m3 | Incld. forms & rebar | Cubic Meters | 5.15 | 1.21 | Hr / Cubic Meters | ||
5 | Mat Foundation | ≤ 25m3 | Incld. forms & rebar | Cubic Meters | 5.72 | 1.34 | Hr / Cubic Meters |
WALLS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Grade Walls,@ 2.4m High | 200mm thick | Incld. forms & rebar | Cubic Meters | 0.500 10.00 0.250 5.000 1.000 0.250 0.125 0.625 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
16.17 | 4.95 | Hr / Cubic Meters |
2 | Grade Walls,@ 4.2m High | 200mm thick | Incld. forms & rebar | Cubic Meters | 20.10 | 6.15 | Hr / Cubic Meters | ||
3 | Grade Walls,@ 4.2m High | 300mm thick | Incld. forms & rebar | Cubic Meters | 14.07 | 4.31 | Hr / Cubic Meters | ||
4 | Grade Walls,@ 3.6m High | 400mm thick | Incld. forms & rebar | Cubic Meters | 9.38 | 2.87 | Hr / Cubic Meters | ||
5 | Grade Walls,@ 5.5m High | 400mm thick | Incld. forms & rebar | Cubic Meters | 13.53 | 4.14 | Hr / Cubic Meters |
OTHER WORKS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | REMARKS | UNIT | TEAM COMPONENTS | AVE. OUTPUT - HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | |||||||
1 | Handicap Ramp, 1.5m Wide | 1.50 m Wide | Incld. forms, rebar, & finish | Cubic Meters | 9.70 | 2.97 | Hr / Cubic Meters | ||
2 | Roof Deck, screed finish | Not incld. forms & rebar | Cubic Meters | 1.19 | 0.98 | Hr / Cubic Meters | |||
3 | Pile Caps, square / rectangular | ≥ 07.5m3 | Incld. forms & rebar | Cubic Meters | 1.000 5.000 0.250 4.000 0.250 0.375 0.250 0.125 0.125 2.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Crane Truck Concrete Pump Power Tools |
4.20 | 1.15 | Hr / Cubic Meters |
4 | Pile Caps, triangualar / hexagonal | ≥ 0.75m3 | Incld. forms & rebar | Cubic Meters | 4.30 | 1.18 | Hr / Cubic Meters | ||
5 | Retaining walls, gravity, @ 1.2m high | 200mm(top) / 600mm (btm) | Incld. forms & rebar | Cubic Meters | 1.000 9.000 0.500 5.000 0.500 0.375 0.375 0.500 4.000 |
Foreman Carpenter Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump Crane Power Tools |
8.67 | 2.85 | Hr / Cubic Meters |
6 | Retaining walls, retaining, @ 2.4m high | 300mm(top) / 600mm (btm) | Incld. forms, rebar, & footing | Cubic Meters | 0.500 10.00 0.250 5.000 1.000 0.250 0.125 0.625 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
9.38 | 2.87 | Hr / Cubic Meters |
7 | Stairs | 300mm wide | Incld. forms, rebar, & finish | Cubic Meters | 1.000 8.000 0.250 0.125 4.000 0.125 0.125 0.125 0.375 0.125 0.125 4.000 |
Foreman Carpenter Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump Crane Truck Finishing Equipment Power Tools |
102.16 | 36.89 | Hr / Cubic Meters |
8 | Stairs Landing | Incld. forms, rebar, & finish | Cubic Meters | 1.000 10.00 0.125 4.000 1.000 0.375 0.125 0.500 0.125 4.000 |
Foreman Carpenter &Steelman Mason Laborer Equip. Opt. Concrete Vibrator Concrete Pump & Trans Mixer Crane Truck Power Tools |
12.76 | 4.02 | Hr / Cubic Meters |
HELP US
We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.
Don’t forget to hit Like and Share if this blog helped you.
FOLLOW US!
Please like and follow our Facebook page for social media updates.