Concrete Work Productivity Rate

You are currently viewing Concrete Work Productivity Rate
Concrete Work Productivity Rate

The data written below for concrete work productivity rate are the average output per hour of the task or activity. The described activity has a recommended list of teams for labor and equipment. Please take note that these are suggested values and for reference only. Each project has a different approach. Factors, wastage and allowances should be considered while doing estimates.

The list activities indicated below are for Cast-In-Place concrete work. Please take note of the remarks in the activity if the output accounts the productivity for formworks, steelworks and works for finishes.

For other civil works productivity rates, please check below the list of items:
– Masonry works and installation man-hours, please see the link: MASONRY WORK PRODUCTIVITY RATE
– Rebar installation man-hours, please see the link: REBAR PRODUCTIVITY RATE

For other material price list, please check below the list of items:
– Reinforced concrete pipe, please see the link: RCP PIPE PRICE LIST
– Ready mixed concrete, please see the link: RMC PRICE LIST
– Rebar steel price list, please see the link: REBAR PRICE LIST
– I beam price list, please see the link: I-BEAM PRICE LIST

CONCRETE WORK PRODUCTIVITY RATE

BASE

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Base, granolithic 25 mm x 127mm Incld. forms & rebar Linear Meters 0.125 2.000 1.000 1.000 1.000 2.000 Foreman Mason Carpenter Steelman Laborer Finishing Eqpt 0.57 0.22 Hr / Linear Meters
2 Base, granolithic 25 mm x 127mm (High cove) Incld. forms & rebar Linear Meters 0.77 0.30 Hr / Linear Meters

BEAMS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Beams, 745 kg/m 3.0 m span Incld. forms & rebar Cubic Meters 1.000
10.00

4.000
0.250
1.000
0.375

0.125



0.500
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
27.30 8.61 Hr / Cubic Meters
2 Beams, 745 kg/m 7.5 m span Incld. forms & rebar Cubic Meters 22.02 6.94 Hr / Cubic Meters

COLUMNS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Square Columns, @ 4.2 m high 300mm x 300mm (max) Incld. forms & rebar Cubic Meters 1.000
10.00

4.000
0.250
1.000
0.375

0.125


0.500
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equipt. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
50.56 15.94 Hr / Cubic Meters
2 Square Columns, @ 4.2 m high 600mm x 600mm (max) Incld. forms & rebar Cubic Meters 29.67 9.36 Hr / Cubic Meters
3 Square Columns, @ 4.2 m high 900mm x 900mm (max) Incld. forms & rebar Cubic Meters 23.14 7.30 Hr / Cubic Meters
4 Rectangular Columns, @ 4.2 m high 300mm x 1600mm (max) Incld. forms & rebar Cubic Meters 30.33 9.57 Hr / Cubic Meters
5 Round Columns, Tied, @ 4.2 m high 300mm Diameter Incld. forms & rebar Cubic Meters 1.000
9.000

5.000
0.250
1.00
0.375

0.125



0.500
0.125
2.000
Foreman
Carpenter &Steelman
Laborer
Mason
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
34.13 6.56 Hr / Cubic Meters
6 Round Columns, Tied, @ 4.2 m high 600mm Diameter Incld. forms & rebar Cubic Meters 22.75 4.38 Hr / Cubic Meters
7 Round Columns, Tied, @ 4.2 m high 900mm Diameter Incld. forms & rebar Cubic Meters 16.65 3.20 Hr / Cubic Meters
8 Max Rebar, Round Columns, Tied, @ 4.2 m high 900mm Diameter Incld. forms & rebar Cubic Meters 28.44 5.47 Hr / Cubic Meters

ELEVATED SLABS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Elevated Flat Slabs, Suspended, @ 600kg/m2 6.0m Span Incld. forms, rebar, & finish Cubic Meters 1.000
10.00

4.000
0.250
1.000

0.375

0.125


0.500
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equipt. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
9.29 2.93 Hr / Cubic Meters
2 Elevated Flat Slabs, Suspended, @ 600kg/m2 8.4m Span Incld. forms, rebar, & finish Cubic Meters 6.83 2.15 Hr / Cubic Meters
3 Elevated Flat Slabs, Suspended, @ 600kg/m2 4.6m Span Incld. forms, rebar, & finish Cubic Meters 9.10 2.87 Hr / Cubic Meters
4 Elevated Flat Slabs, Suspended, @ 600kg/m2 7.4m Span Incld. forms, rebar, & finish Cubic Meters 7.58 2.39 Hr / Cubic Meters
5 Elevated Waffle Slabs, Suspended, @ 600 kg/m2 6.0m Span Incld. forms, rebar, & finish Cubic Meters 1.000
10.00

4.000
0.250
1.000

0.375

0.125


0.500
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
11.38 3.59 Hr / Cubic Meters
6 Elevated Waffle Slabs, Suspended, @ 600 kg/m2 9.2m Span Incld. forms, rebar, & finish Cubic Meters 9.10 2.87 Hr / Cubic Meters
7 Elevated Joist Slab, Suspended, @ 600 kg/m2 4.6m Span , 762 Pans Incld. forms, rebar, & finish Cubic Meters 11.57 3.65 Hr / Cubic Meters
8 Elevated Joist Slab, Suspended, @ 600 kg/m2 7.2m Span, 762 Pans Incld. forms, rebar, & finish Cubic Meters 9.48 2.99 Hr / Cubic Meters
9 Elevated one way beam, Suspended, @ 600 kg/m2 7.6m Span Incld. forms, rebar, & finish Cubic Meters 14.37 4.53 Hr / Cubic Meters
10 Elevated two way beam, Suspended, @ 600 kg/m2 7.6m Span Incld. forms, rebar, & finish Cubic Meters 12.47 3.93 Hr / Cubic Meters
11 Elevated slabs (concreting & finish only) 150mm Thick Incld. forms, rebar, & finish Square Meters 0.5
6.00
2.00
2.00
1.00

1.00

2.00

2.00
Foreman
Laborer
Mason
Carpenter
Equip. Opt.
Concrete Pump
Concrete Vibrator
Finishing Eqpt
0.22 0.10 Hr / Square Meters
12 Elevated slabs (concreting & finish only) 64 mm Thick Floor Incld. forms, rebar, & finish Square Meters 0.22 0.10 Hr / Square Meters

FOUNDATION

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Spread Footings ≤ 0.75m3 Incld. forms, rebar, & finish Cubic Meters 1.000
5.000

4.000
0.250
0.250
0.375

0.125

0.250
0.125
2.000
Foreman
Carpenter &Steelman
Laborer
Mason
Equip. Opt.
Concrete Vibrator
Concrete Pump
Crane
Truck
Power Tools
5.88 1.61 Hr / Cubic Meters
2 Spread Footings ≥ 4.0m3 Incld. forms & rebar Cubic Meters 4.90 1.34 Hr / Cubic Meters
3 Mat Foundation ≥ 1000m3 Incld. forms & rebar Cubic Meters 0.500
7.000

0.250
4.000
0.500

0.250

0.250
0.250
0.125

2.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Crane
Truck
Concrete Pump
Power Tools
4.20 0.99 Hr / Cubic Meters
4 Mat Foundation ≥ 25 m3 to ≤ 500m3 Incld. forms & rebar Cubic Meters 5.15 1.21 Hr / Cubic Meters
5 Mat Foundation ≤ 25m3 Incld. forms & rebar Cubic Meters 5.72 1.34 Hr / Cubic Meters

WALLS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Grade Walls,@ 2.4m High 200mm thick Incld. forms & rebar Cubic Meters 0.500
10.00

0.250
5.000
1.000
0.250

0.125



0.625
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
16.17 4.95 Hr / Cubic Meters
2 Grade Walls,@ 4.2m High 200mm thick Incld. forms & rebar Cubic Meters 20.10 6.15 Hr / Cubic Meters
3 Grade Walls,@ 4.2m High 300mm thick Incld. forms & rebar Cubic Meters 14.07 4.31 Hr / Cubic Meters
4 Grade Walls,@ 3.6m High 400mm thick Incld. forms & rebar Cubic Meters 9.38 2.87 Hr / Cubic Meters
5 Grade Walls,@ 5.5m High 400mm thick Incld. forms & rebar Cubic Meters 13.53 4.14 Hr / Cubic Meters

OTHER WORKS

ITEM NO. ACTIVITY / DESCRIPTION SIZE / DIMENSION REMARKS UNIT TEAM COMPONENTS AVE. OUTPUT - HOURS / UNIT
LABOR EQUIPMENT UNIT
1 Handicap Ramp, 1.5m Wide 1.50 m Wide Incld. forms, rebar, & finish Cubic Meters 9.70 2.97 Hr / Cubic Meters
2 Roof Deck, screed finish Not incld. forms & rebar Cubic Meters 1.19 0.98 Hr / Cubic Meters
3 Pile Caps, square / rectangular ≥ 07.5m3 Incld. forms & rebar Cubic Meters 1.000
5.000

0.250
4.000
0.250
0.375

0.250
0.125
0.125

2.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Crane
Truck
Concrete Pump
Power Tools
4.20 1.15 Hr / Cubic Meters
4 Pile Caps, triangualar / hexagonal ≥ 0.75m3 Incld. forms & rebar Cubic Meters 4.30 1.18 Hr / Cubic Meters
5 Retaining walls, gravity, @ 1.2m high 200mm(top) / 600mm (btm) Incld. forms & rebar Cubic Meters 1.000
9.000
0.500
5.000
0.500

0.375

0.375

0.500
4.000
Foreman
Carpenter
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump
Crane
Power Tools
8.67 2.85 Hr / Cubic Meters
6 Retaining walls, retaining, @ 2.4m high 300mm(top) / 600mm (btm) Incld. forms, rebar, & footing Cubic Meters 0.500
10.00

0.250
5.000
1.000
0.250

0.125



0.625
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
9.38 2.87 Hr / Cubic Meters
7 Stairs 300mm wide Incld. forms, rebar, & finish Cubic Meters 1.000
8.000
0.250
0.125
4.000
0.125
0.125

0.125

0.375

0.125
0.125
4.000
Foreman
Carpenter
Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump
Crane
Truck
Finishing Equipment
Power Tools
102.16 36.89 Hr / Cubic Meters
8 Stairs Landing Incld. forms, rebar, & finish Cubic Meters 1.000
10.00

0.125
4.000
1.000
0.375

0.125



0.500
0.125
4.000
Foreman
Carpenter &Steelman
Mason
Laborer
Equip. Opt.
Concrete Vibrator
Concrete Pump & Trans Mixer
Crane
Truck
Power Tools
12.76 4.02 Hr / Cubic Meters

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Don’t forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our Facebook page for social media updates.

facebook.com/theprojectestimate