EQUIPMENT and TOOLS RENTAL RATES

Rental means the rate you will pay for the hire of equipment or the cost you will charge to your project for borrowing an equipment. Either way, equipment and tools that you will use on your project must be assessed well. Rates will vary based on the condition, functionality, and maintenance as what we have discussed on BASIC LABOR ESTIMATION GUIDE since this will affect your productivity.

For other project estimation reference, please check the other items below:
– Excavation man hours, please check the link: EXCAVATION MAN HOURS
Construction labor rates, please check the link: CONSTRUCTION LABOR COST
– Materials for form works, please check the link: FORMWORK PRICE LIST
– Materials for scaffolding works, please check the link: SCAFFOLDING PRICE LIST
– Consumable materials, please check the link: COMMON AND CONSUMABLE MATERIALS PRICE

CONSTRUCTION RENTAL RATES

MAIN EQUIPMENT

Philippines Construction Equipment Rates
Item No.EquipmentRate per Hour
Cost Range
1Crawler Loader (80kW / 1.5 – 2.0 cu.m)28303670
2Crawler Dozer (125kW)32204850
3Wheel Loader (2.0 – 3.0 cu.m)28104200
4Backhoe Crawler (0.75 – 1.0 cu.m)24203560
5Backhoe / Pavement Breaker (1.5 cu.m)41105240
6Motor Grader ( 90 – 100 kW)21202670
7Pneumatic Tire Roller ( 20 – 24 MT)27403360
8Vibratory Drum Roller ( 10 – 14 MT)27003150
9Dump Truck ( 8.0 – 12.0 cu.m)16502100
10Cargo Truck Small (5 – 8 MT)12301460
11Cargo Truck Small (10 – 15 MT)15501910
12Transit Mixer (5.0 -8.0 cu.m)18302430
13Concrete Batching Plant (80 – 100 cu.m/hr)32505230
14Concrete Trimmer/Slipform Paver (1 meter width)42504820
15Asphalt Distributor Truck (2500 – 3500 Gallons)17002340
16Asphalt Finisher (3 meter width)27303090
17Truck with Boom, small (6-10 MT)14501760
18Truck with Boom, small (12 – 15 MT)18602450
19Crawler Crane (21-25 MT)27803560
20Diesel Pile Hammer19152369

SUPPORT EQUIPMENT

Item No.EquipmentRate per Hour
Cost Range
21Vibratory Pile Driver9261121
22Bagger Mixer (1 – 2 bags)480696
23Concrete Vibrator402471
24Air Compressor – Small347419
25Air Compressor – Big677818
26Bar Cutter292321
27Bar Bender384422
28Jack Hammer309340
29Tamping Rammer297331
30Welding Machine, Portable, 300A662702
31Welding Machine, 600A8311038
32Generator Set 15-25kVA452581
33Generator Set 50kVA809977
34Sump Pump (Dewatering), 0.75 – 2HP199228
35Sump Pump (Dewatering), 5HP397456
36Road Paint Stripper181192
37Road Paint Applicator470603

If your company owns a specific equipment, it will be easier to evaluate since you can verify the maintenance history of that equipment. You can add the cost for a mechanic, parts replacement and maintenance the equipment will need during the period of your project. From that analysis you made, you can assess if it will be better to purchase a new equipment rather than to use an old one because of the incremental cost due to maintenance and parts replacement.  

Purchasing new equipment will always make your project cost proposal high. What we usually do is that even though we purchased a new equipment for that project we still use the rental rates on our estimate since we foresee that we can use it to our other future projects. This will be a great advantage since brand new will be less prone to breakdowns that can cause delays on the project.

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Dont forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our facebook page for social media updates.

https://www.facebook.com/theprojectestimate