The data written below for rebar productivity rate are the average output per hour of the task or activity. The described activity has a recommended list of teams for labor and equipment. Please take note that these are suggested values and for reference only. Each project has a different approach. Factors, wastage and allowances should be considered while doing estimates.
For other civil works productivity rates, please check below the list of items:
– Masonry works and installation man-hours, please see the link: MASONRY WORK PRODUCTIVITY RATE
– Concreting works and installation man-hours, please see the link: CONCRETE WORK PRODUCTIVITY RATE
For other material price list, please check below the list of items:
– Reinforced concrete pipe, please see the link: RCP PIPE PRICE LIST
– Ready mixed concrete, please see the link: RMC PRICE LIST
– Rebar steel price list, please see the link: REBAR PRICE LIST
– I beam price list, please see the link: I-BEAM PRICE LIST
REBAR PRODUCTIVITY RATE
REINFORCING BAR
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | UNIT | TEAM COMPONENTS | AVE. OUTPUT – HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|
LABOR | EQUIPMENT | UNIT | ||||||
1 | Beams & Girders | 10 mm to 25 mm | Metric Ton |
0.25 4.00 2.00 0.25 1.00 0.125 0.125 |
Foreman Steelman Laborer / Helper Equipment Operator Power Tools Crane Low Bed Truck |
45.50 | 8.75 | Hrs / Metric Ton |
2 | Beams & Girders | 25 mm to 40 mm | Metric Ton | 30.00 | 9.00 | Hrs / Metric Ton | ||
3 | Columns | 10 mm to 25 mm | Metric Ton | 42.00 | 12.60 | Hrs / Metric Ton | ||
4 | Columns | 25 mm to 40 mm | Metric Ton | 35.00 | 10.50 | Hrs / Metric Ton | ||
5 | Spirals | 10 mm to 350mm | Metric Ton | 35.00 | 10.50 | Hrs / Metric Ton | ||
6 | Elevated Slabs | 10 mm to 25 mm | Metric Ton | 23.33 | 7.00 | Hrs / Metric Ton | ||
7 | Footings | 10 mm to 25 mm | Metric Ton | 30.00 | 9.00 | Hrs / Metric Ton | ||
8 | Footings | 25 mm to 40 mm | Metric Ton | 23.33 | 7.00 | Hrs / Metric Ton | ||
9 | Slab on Grade | 10 mm to 25 mm | Metric Ton | 26.25 | 7.88 | Hrs / Metric Ton | ||
10 | Walls | 10 mm to 25 mm | Metric Ton | 23.33 | 7.00 | Hrs / Metric Ton | ||
11 | Walls | 25 mm to 40 mm | Metric Ton | 19.09 | 5.73 | Hrs / Metric Ton | ||
12 | Typical in Place | 10 MT (Ave.) | Metric Ton | 38.18 | 11.45 | Hrs / Metric Ton | ||
13 | Typical in Place | 45 MT (Ave.) | Metric Ton | 30.00 | 9.00 | Hrs / Metric Ton |
HANDLING OF REBAR
ITEM NO. | ACTIVITY / DESCRIPTION | UNIT | TEAM COMPONENTS | AVE. OUTPUT – HOURS / UNIT | |||
---|---|---|---|---|---|---|---|
14 | Unloading, handling, & sorting steel reinforcement | Metric Ton | 0.25 4.00 2.00 0.50 0.50 0.50 0.50 |
Foreman Steelman Laborer / Helper Equipment Operator Eqpt. Op. Oiler Crane Low Bed Truck |
0.76 | 0.11 | Hr / Metric Ton |
STEEL DOWELS
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | UNIT | TEAM COMPONENTS | AVE. OUTPUT – HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|
15 | Steel Dowels, 600mm Long | 10 mm | Piece | 0.125 2.00 1.00 |
Foreman Steelman Laborer / Helper |
0.07 | 0.00 | Hr / Piece |
16 | Steel Dowels, 600mm Long | 15 mm | Piece | 0.09 | 0.00 | Hr / Piece | ||
17 | Dowels, Steel, 600mm Long | 20 mm | Piece | 0.10 | 0.00 | Hr / Piece | ||
18 | Steel Dowels, more than 600mm | > 20mm | Kilogram | 0.09 | 0.00 | Hr / Kilogram | ||
19 | Smooth dowels, 300mm long | 10 mm | Piece | 0.26 | 0.00 | Hr / Piece | ||
20 | Smooth dowels, 300mm long | 16 mm | Piece | 0.31 | 0.00 | Hr / Piece | ||
21 | Dowel caps, 125mm long | 20 mm | Piece | 0.34 | 0.00 | Hr / Piece | ||
22 | Dowel caps, 125mm long | 32 mm | Piece | 0.04 | 0.00 | Hr / Piece |
SPLICING OF REBAR
ITEM NO. | ACTIVITY / DESCRIPTION | SIZE / DIMENSION | UNIT | TEAM COMPONENTS | AVE. OUTPUT – HOURS / UNIT | |||
---|---|---|---|---|---|---|---|---|
23 | Buttweld column bar splice | 35 mm | Piece | 1.0 4.00 2.00 1.00 |
Foreman Steelman Laborer / Helper Power Tools |
0.84 | 0.24 | Hr / Piece |
24 | Column splice clamp, sleeve/wedge | 35 mm | Piece | 0.49 | 0.14 | Hr / Piece | ||
25 | Mechanical splice sleeve type | 35 mm | Pc | 1.07 | 0.31 | Hr / Piece | ||
26 | Splicing Straight Rebar, mechanical threading | 35 mm | Piece | 0.98 | 0.28 | Hr / Piece | ||
27 | Splicing Straight Rebar, mechanical threading | 40 mm | Piece | 1.31 | 0.37 | Hr / Piece | ||
28 | Splicing Bent Rebar, mechanical threading | 40 mm | Pc | 1.63 | 0.47 | Hr / Piece |
HELP US
We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.
Don’t forget to hit Like and Share if this blog helped you
FOLLOW US!
Please like and follow our Facebook page for social media updates.