The following are duct installation cost reference for ductworks installation such as installation of straight ducts and fittings.

For flexible, spiral, and rectangular duct, please click the link VENTILATION DUCT PRICE LIST

For louvers, diffusers, dampers and air grill, please click the link DAMPERS, DIFFUSER, GRILLE AND LOUVER PRICE LIST

DUCT WORKS INSTALLATION COST REFERENCE

STRAIGHT DUCT INSTALLATION

Below are the installation man hours for straight duct based on the perimeter dimension of duct and the total area of the duct installed.

Duct Dimension

For example, you have the following duct to install with dimension, 300mm(height) X 500mm(width) X 10meters(length). The perimeter value of your duct is 1.6 meters, based on the table, the value falls in between of 1.22 and 1.95. For the exact value, you can use interpolation but just to be safe always on your estimation you can use the next higher value which is 1.95. The corresponding value of man hours at 1.95 perimeter for installation is 2.60 hrs per square meter. If you have a total area of 16 sq.m., the total man hours for the installation is 41.6 hrs. If you pay 75Php/hr, the total cost will be Php 3,120.00. To get the actual time for the work to get done, the value 41.6hrs will be divided on how many man-power you have for the installation

 
DIMENSIONS MANHOURS
Duct Perimeter Manhours for Fabrication Manhours for Installation
feet meter per sq. ft. per sq.m per sq. ft. per sq.m
4 1.22 0.154 1.656 0.242 2.603
6.4 1.95 0.154 1.656 0.242 2.603
8 2.44 0.176 1.893 0.253 2.721
10 3.05 0.176 1.893 0.253 2.721
11.2 3.41 0.176 1.893 0.264 2.840
12 3.66 0.187 2.011 0.286 3.076
14.6 4.45 0.209 2.248 0.308 3.313
16 4.88 0.22 2.366 0.33 3.550
17 5.18 0.242 2.603 0.352 3.786
20 6.10 0.253 2.721 0.374 4.023
25 7.62 0.253 2.721 0.385 4.14
28.6 8.72 0.253 2.721 0.385 4.141
32 9.76 0.264 2.840 0.407 4.378
34.5 10.52 0.264 2.840 0.407 4.378

DUCT FITTINGS INSTALLATION

Below are the installation man hours for duct fittings installation. The installation man hours are per piece or per item.

 
DIMENSION MANHOURS
Duct Perimeter Elbow Tees Wyes Tap-ins Offset Transition
feet meter mnhr/pc mnhr/pc mnhr/pc mnhr/pc mnhr/pc
4 1.22 0.297 0.462 0.528 0.297 0.385
6.4 1.95 0.495 0.748 0.88 0.495 0.495
8 2.44 0.616 0.913 1.056 0.616 0.616
10 3.05 0.759 1.144 1.342 0.759 0.759
11.2 3.41 0.858 1.287 1.507 0.858 0.858
12 3.66 0.913 1.375 1.606 0.913 0.913
14.6 4.45 1.1 1.65 1.936 1.1 1.1
16 4.88 1.221 1.815 2.134 1.221 1.221
17 5.18 1.287 1.936 2.266 1.287 1.287
20 6.10 1.518 2.277 2.662 1.518 1.518
25 7.62 1.903 2.86 3.322 1.903 1.903
28.6 8.72 2.167 3.256 3.795 2.167 2.167
32 9.76 2.431 3.652 4.257 2.431 2.431
34.5 10.52 2.629 3.927 4.587 2.629 2.629

HELP US

We want to improve this website so we need your help. Please send us your recommendations, suggestion, and request. Click this for the SUGGESTION FORM PAGE.

Dont forget to hit Like and Share if this blog helped you.

FOLLOW US!

Please like and follow our facebook page for social media updates.

https://www.facebook.com/theprojectestimate